Would you please provide an update on the current construction project at Tanglewood?

Posted by:

The project is in full swing.  The new parking lot will be completed before early voting October 23 – November 3 (to be held at Tanglewood) and the November 7 election.  In addition, several new sidewalks will be installed on the campus.  Early voters will be able to park on the temporary lot and teachers will be on the new lot.  The cafeteria project is also moving along.  The old kitchen has been removed and infrastructure work in that area is well underway.  Over Thanksgiving break, some of the work will be completed that needs to be done when children are not in attendance.  (Clayton will not be on the campus during Thanksgiving or Winter Break).  Plans for the restrooms and the library expansion are being developed at this time.